|
WHITEMOSS
LANDFILL SITE
The
Whitemoss Landfill owned and operated by J Routledge &
Sons (Liverpool) Ltd has been in operation for the last ten
years.
The site
is located to the South of the M58, 500 metres West of Junction
4, on Whitemoss Road South, Skelmersdale. Junction 26 of the
M6 is 6 km away and so the site is well connected to the Region's
road network.
Skelmersdale
lies to the North of the Motorway, whilst open fields predominate
to the South, East and West; Liverpool is 15 km to the South
West and Manchester 35 km to the East. Within 50 km of the
site lie Lancashire and Cheshire, Merseyside and Greater Manchester.
The site is located in the central part of the Mersey Belt,
a major centre of manufacturing and commerce.
The site
lies on a minor aquifer of intermediate vulnerability. It
was formerly a worked out peat extraction partially backfilled
construction waste landfill. Beneath the ground lies boulder
clay of 8 m thickness, and beneath that mudstone.
A number
of technical studies have been undertaken to accurately characterise
the hydrogeology of the site and its surrounding area. A comprehensive
report dated January 1997 was submitted to the Environment
Agency (EA) and approved by them to demonstrate that the site
when engineered to exacting design specifications would not
have any unacceptable discharge of pollution at any stage
in its life cycle.
Subsequently,
the EC Groundwater, Landfill and in October 2000 Water Framework
Directive were ratified. A further report was prepared and
submitted in June 2003 to the EA "Groundwater & Surface
Water Risk Assessment", which confirmed that the site
complies with the most recent requirements of E U Law.
Many
people are unaware of the care with which a modern landfill
is constructed and operated. It is generally thought that
a landfill merely comprises a hole in the ground, created
either by natural contours or more usually former mineral
workings.
In the
case of Whitemoss as least this could not be further from
the truth.
Firstly,
the site was chosen for its location, rather than the chance
of a pre-existing void. The geology and hydrogeology were
extensively investigated before the decision was made to create
the landfill. The geology and hydrogeology are exceptionally
well suited to the purpose being a low risk ground water situation
and the presence of boulder clay that is again exceptionally
well suited in terms of its potential permeability and its
engineering characteristics.
A demand
locally for the minerals of clay and mudstone, for civil engineering
and brick manufacture, complete a picture of a rare combination
of factors.
The next
part of the process of creating a landfill facility is to
seek Planning Permission. A design was commissioned from a
respected consultancy, Wardell Armstrong, studies undertaken,
extensive discussions with the precursor of the EA, the regional
Waste Regulation Authority and an Application submitted.
Once Planning
Permission is obtained, a Waste Management Licence, now an
IPPC Permit must be obtained. The EA agree the engineering
details supplied by the Consulting Engineer. Once they are
satisfied that a robust and effective lining and capping system
will protect the environment, work can commence.
A Permit
is produced which details the means by which ground and surface
water will be protected long term, and the site managed to
reduce the risk of nuisance or health risk to the human, and
indeed animal population.
The
permit holder must agree with the EA a means by which the
future monitoring and restoration of the surface of the site
after closure is financially secure.
The operator
has to be declared as “Fit & Proper” to operate
such a site and pass a series of twelve detailed assessments
as to his competence carried out by external assessors. Each
module examination comprise written and oral work, together
with a portfolio of documented evidence further proving the
ability of the candidate.
How is
a Landfill Site constructed so as to ensure protection of
the environment?
The lining
system in the case of Whitemoss comprises a composite system
of clay, High Density Polythene (HDPE) drainage systems and
protection blankets.
A system
of drains is created in the base below the lining system and
where necessary the sides of the excavation. This is then
led to a pumping chamber so that groundwater from outside
of the excavation can be prevented from building up behind
the composite line.
Calculations
based on the tested physical characteristics of the clay determine
the thickness of the clay liner. On site won clay is stockpiled.
The stockpile is tested for its compliance with the specification
as to particle size, density, moisture content and plasticity.
Only material from the tested stockpile can be incorporated
into the works.
A qualified
engineer is selected and his c.v. assessed and approved by
the E.A. He is employed by the third party Construction Quality
Assurance Team. Every detail, at every step is pre-agreed
by the E.A. and under third party Supervision, themselves
audited by periodic visits by the E.A.’s own qualified
engineers.
The clay
is laid in 300mm layers. Each layer is tested on site by a
Nuclear Test Gauge for density and moisture content. The clay
must have an optimum moisture content of 12%. Less, and the
particles won’t bind. More, and it loses mechanical
strength.
The Nuclear
Test Gauge is calibrated periodically (as required by E.A.
guidance) by sand replacement tests conducted by another consultant.
Similarly, Core Samples are sent for Laboratory Analysis for
physical checks to ensure the emplaced clay meets the specification.
The clay is rolled by a vibrating heavy self-propelled roller
four times per layer.
Six layers
were placed on the base of the excavation, between 2 and 3
on the side slopes, themselves constructed to a slope of 1
in 2.5 to millimetric accuracy. Survey by laser computerised
equipment ensures the exact thickness of the layers.
A Specialist
Company of flexible membrane liners and suppliers of HDPE
is selected and engaged. The operatives are certified as being
trained and competent in the welding of the HDPE.
Each
roll is numbered and bears its own certificate of conformity
from the manufacturer. Samples are taken from every fourth
roll and sent for analysis as to thickness, plasticity, content
of carbon black and other characteristics.
A trench
is excavated at the top of the side slopes. The trench itself
is to support the HDPE membrane and is designed to allow the
liner to creep downwards slightly under the frictional pull
of the weight of waste laid against it. This reduces the possibility
of the HDPE liner being reduced in thickness by this downward
pulling motion.
Each panel
is then welded to its neighbour. This is achieved by a special
self-propelled welding machine, which creates a double weld
with a small air gap between the two welds. Once the weld
is complete the air gap is filled with compressed air. A pressure
gauge measures any drop in pressure, this proving if there
is a leak. If a leak is detected then it is then located and
a patch applied. An electrical conductor is incorporated within
the hand weld so that the weld can be checked for water tightness.
All of
this is supervised by the third party Construction Quality
Assurance Engineer.
Finally the clay is in place, the under drainage connected
and a drainage blanket and pipes are laid on top of the HDPE
& drainage blanket. The drainage medium has to be chemically
analysed, tested for its physical characteristics and laid
under third party supervision.
The next
step is that a further consultant is brought in – in
our case from the Czech Republic to test the entire installation
system.
Electrodes
are placed beneath the HDPE and above in the drainage medium.
A current is passed through and any leaks are detected, and
remediated if necessary. The system is then re-checked.
All of
the records, every weld test, every core sample result, survey
of clay thickness, survey of every single panel and weld and
a summary are incorporated into a report submitted by the
Consulting Engineer to the Environment Agency. Details of
laboratory test results on the leachate drainage blanket to
ensure that the chosen medium has the correct chemical make-up,
permeability and geotechnical properties are supplied before
the drainage blanket is emplaced, under third party Construction
Quality Assurance supervision.
A protective
layer of geofabric is laid beneath the drainage medium, and
appropriate laboratory tests to ensure its strength under
the compressive effects of the waste undertaken to prove its
resistance to penetration.
Once the
drainage blanket, which extends up the sides, or batters,
of the cell is in place then the first 1m layer of selected
waste is emplaced. This waste is selected so as to exclude
items such as long, hard, objects that could penetrate the
protective layers of the liner below.
A site
road is built to enable road vehicles to make the descent
into the cell safely in all weather, ensuring that the vehicles
tyres are protected from objects that could damage them, and
that the vehicle stability is ensured.
Waste
that meets the site licence (Permit) is laid in layers in
such a way that it remains physically stable, enables precipitation
to run through it for collection and treatment, and provides
a safe working platform for machines and customers transport.
Whitemoss
is permitted only for wastes that are classed as Hazardous.
Although a waste stream may be classed as Hazardous under
European and National Legislation, the actual risk posed may
in fact be quite small. A television becomes "Hazardous"
once it is discarded, though moments before it was sat happily
in the corner of its owners lounge.
All wastes
offered for disposal to Whitemoss have to comply with strict
acceptance criteria. As would be expected, this excludes liquids,
highly flammable, corrosive and oxidising wastes and Hospital
or Clinical wastes. The criteria also place limits on the
concentrations of substances within the waste to ensure the
safety of people on, and off, the site, and to protect the
environment.
In
addition, all wastes to the site have to be pre-treated to
meet EA requirements.
Boreholes
into the waste extract Landfill Gas of flaring or energy recovery.
Because of the nature of the waste at Whitemoss, little Landfill
Gas is generated.
Rain falling
onto the waste soaks through it to the collection system at
the base of the site.
This water
is then contaminated by contact with the waste. As the site
is lined with a very impermeable liner, accumulation of liquid
has to be carefully managed.
The liquid,
known as leachate, is pumped via a purpose made well to a
holding lagoon where it can be pre-treated if necessary before
discharge to off-site treatment.
Once the
cell has been filled to the levels agreed with the EA and
Planning Authority then a similar procedure to that used to
line the base and sides is adopted. An artificial liner is
placed over a protection layer, and welded to the sides of
the cell. A further mineral liner is laid over the top. Top
soil is then placed on the mineral liner to protect it from
desiccation and erosion.
Trees
and other vegetation are then planted on the surface.
After
the site has been capped monies set aside during its life
into a special account accessible only for this purpose, are
used to fund its monitoring and replacement of key management
infrastructure (such as pipes, leachate treatment equipment
etc).
In this
way, once the waste management options of reduce, re-use,
recycle have been exhausted the remaining residue can be disposed
of safely. It should be noted that this is the Best Practicable
Environmental Option recognised by all of the major Environment
Campaign Groups.
|